PROGETTO DELLA TRAVE DI COPERTURA
Prendo:
ACCIAIO Fe b 44 k
Cls Rbk 400 Kg/cm2 = 40 N/mm2
ss =2600 Kg/cm2
Rbk -150
sc = 60 + =122.5 Kg/ cm2
4
SCELGO LA BASE :
b = 50 cm
n*sc 15 * 122.5 Kg/ cm2
s =
n*sc + ss 15 * 122.5 Kg/ cm2 + 2600 Kg/ cm2
2 2
r = =
sc (1-s/3)*s 122.5 Kg/ cm2(1-0.414/3)*0.414
921850 Kg*cm
dmin = r M/b = 0.21 = 60.9 cm
50 cm
Scelgo d = 65 cm
AREA TOTALE AS dell'ARMATURA
M 4636800 Kg*cm
AS MIN = = 33.93 cm2
(1-s/3)*d*ss (1- 0.414/3)* 60.97 cm * 2600 Kg/cm2
Scelgo 6 con AS = 36.95 cm2
VERIFICHE:
n (A's + As) 2b(A'sd'+Asd)
POSIZIONE ASSE NEUTRO:
b n (A's + As)2
15* (1.01 cm2 + 33.97 cm2) 2*30 cm ( 1.01 cm2*3 cm + 33.97 cm2 *65 cm)
50cm 15 (1.01 cm2 + 33.97 cm2)
= 27.3 cm
MOMENTO D'INERZIA NELLA SEZIONE OMOGENEIZZATA:
bx3
I0 = + n*A's (x-d') 2 + n*As (d-x) 2 =
3
50cm ( 27.3 cm)3
+ 15* 1.01 cm2 ( 27.3 cm - 3 cm) 2 + 15*33.97 cm2 (65 cm - 27.31 cm) 2 =
3
= 1072271.2 cm4
4636800 Kg*cm
sc = M/ I0 * x = * 27.3 cm = 118.05 kg/ cm2
1072271.2 cm4
118.05 kg/ cm2 < 122.5 kg/ cm2 ( sc ) VERIFICATO
4636800 kg*cm
s's = n* M/ I0 * (x - d') = 15 * * (27.3 cm - 3 cm) = 1576.2 kg/ cm2
1072271.2 cm4
1576.2 kg/ cm2 < 2600 kg/ cm2 ( ss ) VERIFICATO
4636800 kg*cm
ss = n* M/ I0 * (d - x ) = 15 * * (65 cm - 27.3 cm) = 2445.38 kg/ cm2
1072271.2 cm4
2445.38 kg/ cm2 < 2600 kg/ cm2 ( ss ) VERIFICATO
VERIFICA A TAGLIO:
TMax = 15456 Kg
T 15456Kg
t Max = 5.28 Kg/cm2
0.9 * b * d 0.9 * 50 cm * 65 cm
Rbk - 150 400-150
tCO = 7.33 Kg/cm2
Rbk - 150 400-150
tC1 = 21.14 Kg/cm2
35 35
tCO < t Max < tC1
Non sarebbe necessaria armatura a taglio, ma dobbiamo mettere il quantitativo minimo da normativa:
STAFFE a 2 braccia 8 mm con As = 0.5 cm2
Minimo 3 staffe / m2
Passo tra le staffe < 0.8 d (comunque 33.3 cm)
< 0.8 * 65 cm = 52 cm 222f56c
Scelgo un passo tra le staffe di 30cm.
INTERPIANO
Analisi dei carichi
ISOLAMENTO 3 Kg/m2
INTONACO 3 Kg/m2
PAVIMENTO 40 Kg/m2
CALDANA+SOTTOFONDO 127 Kg/m2
PESO TRAMEZZI 241 Kg/m2
CARICO D'ESERCIZIO 200 Kg/m2
q tot 614 Kg/m2
q = 6.14 KN/m2
Spessore solaio L/25 (comunque > 12 cm)
L/25 = 400 cm/25 = 16 cm
Tentativo H = (16,5 + 3) cm g = 2.4 KN/m2
M tot = (q +g) L2 = (6,14 KN / m2 + 2.4 KN / m2 ) (4 m)2 17.08 KN
8 8
T tot = (g+q) L = (6,14 KN / m2 + 2.4 KN / m2 ) =17.08 KN
2 2
Si sceglie un solaio di tipo CELERSAP traliccio , interasse i = 50 cm (R 38/50)
H = 16.5 +3
g = 2.4 KN / m2
MMax = 20.36 KN / m > 17.08 KN / m
240 Kg / m2
g = * 400 cm = 9.6 Kg / cm2
1002
614 Kg / m2
q = * 400 cm = 24.56 Kg / cm2
1002
TRAVE DI PIANO
Per risolvere la struttura applico il Metodo delle Forze:
. convenzione
di segno
. rendo la struttura isostatica mediante la cerniera in B
js B0 = q L 31 jd B0 = q L 32
24 EI 24 EI
jsB1 = MB * L1 jdB1 = MB * L2
3 EI 3 EI
STUDIO LA CONDIZIONE DI CONGRUENZA:
jAB jBC
jAB jsB0 jsB1 jBC jdB0 jdB1
jsB0 jsB1 jdB0 jdB1
q L31 + MB * L1 + qL32 + MB * L2 = 0
24 EI 3 EI 24 EI 3 EI
q ( L31 + L32 ) 34.16 Kg / cm * (450 3 cm3 + 550 3 cm3)
MB = = - - 1099525 Kg *cm
8 (L1+ L2) 8 (450 cm + 550 cm )
VA + VB + VC - qL1 - qL2 = 0
qL1 MB 34.16 Kg / cm * 450cm -1099525 Kg * cm
VA = - = - = 5242.61 Kg
2 L1 2 450 cm
qL2 MB 34.16 Kg / cm * 550cm -1099525 Kg * cm
VC = - = - = 7394.8 Kg
2 L2 2 550 cm
qL1 qL2 1 1
VB = + + MB ( ) =
2 2 L1 L2
34.16 Kg/cm * 450 cm 34.16 Kg/cm * 550 cm 1 1
= + (-1099525 Kg*cm) +
2 2 450 cm 450 cm
= 21478.1 Kg
TAGLIO:
TA = VA = 5242.6 Kg
TC = -VC = 7394.8 Kg
TX - VA + qx = 0 TX (AB) = 0 VA - qx = 0
VA 7394.8 Kg
x = = = 153.47 cm
q 34.16 Kg/cm
TX + VC - qx = 0 TX (CB) = 0 VC - qx = 0
VC 7394.8 Kg
x = = = 216.48 cm
q 34.16 Kg/cm
TCs = VA- qL1 = 5242.6 Kg - 34.16Kg/cm * 450 cm = -10129.4 Kg
TCd = VA- qL1 + VB = -10129.4 Kg - 34.16 Kg/cm * 450 cm + 21478.1 Kg = 11348.7 Kg
MOMENTO:
MA = 0 qx2
MX (AB) = VA * x - = 804581.82 Kg*cm - 402285.9 Kg*cm = 402295.8 Kg*cm
2
MB = 1099525 Kg*cm
qx2
MX (CB) = VC * x - = 1600826.3 Kg*cm - 800430.1 Kg*cm = 800396.1 Kg*cm
2
MC = 0
DIAGRAMMI:
q
= 34.16 Kg*cm
450 cm 550 cm
x =153.5 cm x =216.5 cm
5242.6Kg 21478.1Kg 7394.8Kg
T
PROGETTO DELLA TRAVE DI PIANO
Prendo:
ACCIAIO Fe b 44 k
Cls Rbk 400 Kg/cm2 = 40 N/mm2
ss =2600 Kg/cm2
Rbk -150
sc = 60 + =122.5 Kg/ cm2
4
SCELGO LA BASE :
b = 50 cm
n*sc 15 * 122.5 Kg/ cm2
s =
n*sc + ss 15 * 122.5 Kg/ cm2 + 2600 Kg/ cm2
2 2
r = =
sc (1-s/3)*s 122.5 Kg/ cm2(1-0.414/3)*0.414
1099525 Kg*cm
dmin = r M/b = 0.21 = 40.2 cm
50 cm
Scelgo d = 42 cm
1' 2' 3'
1 2 3
AREA TOTALE AS dell'ARMATURA nella SEZ. 1-1'
M 402295.8 Kg*cm
AS MIN = = 4.46 cm2
(1-s/3)*d*ss (1- 0.414/3)* 40.2 cm * 2600 Kg/cm2
Scelgo 4 con AS = 6.16 cm2
AREA TOTALE AS dell'ARMATURA nella SEZ. 2-2'
M 1099525 Kg*cm
AS MIN = = 12.2 cm2
(1-s/3)*d*ss (1- 0.414/3)* 40.2 cm * 2600 Kg/cm2
Scelgo 4 con AS = 12.57 cm2
AREA TOTALE AS dell'ARMATURA nella SEZ. 3-3'
M 800396.1 Kg*cm
AS MIN = = 8.88 cm2
(1-s/3)*d*ss (1- 0.414/3)* 40.2 cm * 2600 Kg/cm2
Scelgo 2 con AS = 2.26 cm2
2 con AS = 6.28 cm2
AS Tot = 8.56 cm2
VERIFICHE:
NELLA SEZIONE 1-1'
n (A's + As) 2b(A'sd'+Asd)
POSIZIONE ASSE NEUTRO:
b n (A's + As)2
15* (6.28 cm2 + 6.16 cm2) 2*30 cm ( 6.28 cm2*3 cm + 6.16 cm2 *41cm)
30 cm 15 (6.28 cm2 + 6.16 cm2)
= 11.39 cm
MOMENTO D'INERZIA NELLA SEZIONE OMOGENEIZZATA:
bx3
I0 = + n*A's (x-d') 2 + n*As (d-x) 2 =
3
30 cm ( 11.39 cm)3
+ 15* 6.28 cm2 ( 11.39 cm - 3 cm) 2 + 15*6.16 cm2 (41 cm - 11.39 cm) 2 =
3
= 102419.32 cm4
402295.8 Kg*cm
sc = M/ I0 * x = * 11.39 cm = 44.73 kg/ cm2
102419.32 cm4
44.73 kg/ cm2 < 122.5 kg/ cm2 ( sc ) VERIFICATO
402295.8 kg*cm
s's = n* M/ I0 * (x - d') = 15 * * (11.39 cm - 3 cm) = 494.32 kg/ cm2
102419.32 cm4
494.32 kg/ cm2 < 2600 kg/ cm2 ( ss ) VERIFICATO
402295.8 kg*cm
ss = n* M/ I0 * (d - x ) = 15 * * (41 cm - 11.39 cm) = 1744.03 kg/ cm2
102419.32 cm4
1744.03 kg/ cm2 < 2600 kg/ cm2 ( ss ) VERIFICATO
NELLA SEZIONE 2-2'
n (A's + As) 2b(A'sd'+Asd)
POSIZIONE ASSE NEUTRO:
b n (A's + As)2
15*(2.26 cm2 + 12.57 cm2) 2*30 cm ( 3.08 cm2*3 cm + 12.57 cm2 * 41 cm)
= 16.37 cm
30 cm 15 (3.08 cm2 + 12.57 cm2)
MOMENTO D'INERZIA NELLA SEZIONE OMOGENEIZZATA:
bx3
I0 = + n*A's (x-d') 2 + n*As (d-x) 2 =
3
30 cm ( 16.37 cm)3
+ 15* 3.08 cm2 ( 16.37 cm - 3 cm) 2 + 15*12.57 cm2 (41 cm - 16.37 cm) 2 =
3
= 166507.77 cm4
1099525 Kg*cm
sc = M/ I0 * x = * 16.37 cm = 108.09 kg/ cm2
166507.77 cm4
108. 09 kg/ cm2 < 122.5 kg/ cm2 ( sc ) VERIFICATO
1099525 kg*cm
s's = n* M/ I0 * (x - d') = 15 * * (16.37 cm - 3 cm) = 1324.32 kg/ cm2
166507.77 cm4
1324.32 kg/ cm2 < 2600 kg/ cm2 ( ss ) VERIFICATO
1099525 kg*cm
ss = n* M/ I0 * (d - x ) = 15 * * (41 cm - 16.37 cm) = 2439.47 kg/ cm2
166507.77cm4
2439.47 kg/ cm2 < 2600 kg/ cm2 ( ss ) VERIFICATO
NELLA SEZIONE 3-3'
n (A's + As) 2b(A'sd'+Asd)
POSIZIONE ASSE NEUTRO:
b n (A's + As)2
15*(6.28 cm2 + 9.36 cm2) 2*30 cm (6.28 cm2*3 cm + 9.36 cm2 * 41 cm)
= 13.71 cm
30 cm 15 (6.28 cm2 + 9.36 cm2)
MOMENTO D'INERZIA NELLA SEZIONE OMOGENEIZZATA:
bx3
I0 = + n*A's (x-d') 2 + n*As (d-x) 2 =
3
30 cm ( 13.71 cm)3
+ 15* 6.28 cm2 ( 13.71 cm - 3 cm) 2 + 15*9.36 cm2 (41cm - 13.71 cm) 2 =
3
= 141137.08 cm4
800396.1 Kg*cm
sc = M/ I0 * x = * 13.71 cm = 77.75 kg/ cm2
141137.08cm4
77.75 kg/cm2 < 122.5 kg/ cm2 ( sc ) VERIFICATO
800396.1 kg*cm
s's = n* M/ I0 * (x - d') = 15 * * (13.71 cm - 3 cm) = 910.88 kg/ cm2
141137.08 cm4
910.88 kg/ cm2 < 2600 kg/ cm2 ( ss ) VERIFICATO
800396.1 kg*cm
ss = n* M/ I0 * (d - x ) = 15 * * (41 cm - 13.71 cm) = 2321 kg/ cm2
141137.08 cm4
2321 kg/ cm2 < 2600 kg/ cm2 ( ss ) VERIFICATO
VERIFICA A TAGLIO:
TMax = 11348.7 Kg
T 11348.7Kg
t Max = 10.25 Kg/cm2
0.9 * b * d 0.9 * 30 cm * 41 cm
Rbk - 150 400-150
tCO = 7.33 Kg/cm2
Rbk - 150 400-150
tC1 = 21.14 Kg/cm2
35 35
tCO < t Max < tC1
nb * As ss 2 * 0.5 cm2 * 2600 Kg/cm2
Smin = = 8.45 cm
t Max* b 10.25 Kg/cm2 * 30 cm
Tengo un passo tra le staffe di 9 cm
INSERISCO UNA ROMPITRATTA
q = 6.14 KN
Spessore solaio L/25 (comunque > 12 cm)
400 cm
L/25 = = 16 cm
25
Tentativo H= 16.5 + 3 cm g = 2.4 KN/m2 (peso proprio solaio)
(q+g)*L2 (6.14 KN/m2 + 2.4 KN/m2 )* 4 m2
Mtot = = 17.08 KN*m
8 8
(q+g)*L2 (6.14 KN/m2 + 2.4 KN/m2 )* 4 m
Ttot = = 17.08 KN*m
2 2
Si sceglie un solaio di tipo CELERSAP traliccio
Interasse i = 50 cm (R 38/50)
H = 16.5 + 3
g = 2.4 KN/m2
MMax = 20.36 KN/m > 17.08 KN/m
240
g = Kg/ m2 * 400 cm = 9.6 Kg/ cm
1002
614
g = Kg/ m2 * 400 cm = 24.56 Kg/ cm
1002
TRAVE DI PIANO
PROGETTO DELLA TRAVE DI PIANO
MMax = 6148800 Kg*cm
Prendo:
ACCIAIO Fe b 44 k
Cls Rbk 400 Kg/cm2
ss =2600 Kg/cm2
Rbk -150
sc = 60 + =122.5 Kg/ cm2
4
SCELGO LA BASE :
b = 62 cm
n*sc 15 * 122.5 Kg/ cm2
s =
n*sc + ss 15 * 122.5 Kg/ cm2 + 2600 Kg/ cm2
2 2
r = =
sc (1-s/3)*s 122.5 Kg/ cm2(1-0.414/3)*0.414
6148800 Kg*cm
dmin = r M/b = 0.21 = 66.13 cm
62 cm
Scelgo d = 67 cm
AREA TOTALE AS dell'ARMATURA
M 6148800 Kg*cm
AS MIN = = 41.48 cm2
(1-s/3)*d*ss (1- 0.414/3)* 66.13 cm * 2600 Kg/cm2
Scelgo 7 28 con AS = 43.10 cm2
VERIFICHE:
n (A's + As) 2b(A'sd'+Asd)
POSIZIONE ASSE NEUTRO:
b n (A's + As)2
15* (2.26 cm2 + 43.1 cm2) 2*30 cm ( 2.62 cm2*3 cm + 43.1 cm2 *67 cm)
= 28 cm
62cm 15 (2.62 cm2 + 43.1 cm2)
MOMENTO D'INERZIA NELLA SEZIONE OMOGENEIZZATA:
bx3
I0 = + n*A's (x-d') 2 + n*As (d-x) 2 =
3
62 cm ( 28 cm)3
+ 15 * 2.26 cm2 ( 28 cm - 3 cm) 2 + 15 * 43.1 cm2 (67 cm - 28 cm) 2 =
3
= 1458188.667 cm4
6148800 Kg*cm
sc = M/ I0 * x = * 28 cm = 118.06 kg/ cm2
1458188.667 cm4
118.06 kg/ cm2 < 122.5 kg/ cm2 ( sc ) VERIFICATO
6148800 kg*cm
s's = n* M/ I0 * (x - d') = 15 * * (28 cm - 3 cm) = 1582.5 kg/ cm2
1458188.667.2 cm4
1582.5 kg/ cm2 < 2600 kg/ cm2 ( ss ) VERIFICATO
6148800kg*cm
ss = n* M/ I0 * (d - x ) = 15 * * (67cm - 28 cm) = 2468.7 kg/ cm2
1458188.667 cm4
2468.7 kg/ cm2 < 2600 kg/ cm2 ( ss ) VERIFICATO
VERIFICA A TAGLIO:
TMax = 20496 Kg
T 20496 Kg
t Max = 5.48 Kg/cm2
0.9 * b * d 0.9 * 62 cm * 67 cm
Rbk - 150 400-150
tCO = 7.33 Kg/cm2
Rbk - 150 400-150
tC1 = 21.14 Kg/cm2
35 35
tCO < t Max < tC1
Non sarebbe necessaria armatura a taglio, ma dobbiamo mettere il quantitativo minimo da normativa:
STAFFE a 2 braccia 8 mm con As = 0.5 cm2
Minimo 3 staffe / m2
Passo tra le staffe < 0.8 d (comunque 33.3 cm)
< 0.8 * 67 cm = 53.6 cm
Scelgo un passo tra le staffe di 30 cm.
PILASTRI
gT1 = H * b * 2500 Kg/m2 * i = 0.4 m * 0.3 m * 5 m * 2500 Kg/ m2 = 1500 Kg
gT2 = H * b * 2500 Kg/m2 * i = 0.44 m * 0.3 m * 5 m * 2500 Kg/ m2 = 1650 Kg
gT3 = H * b * 2500 Kg/m2 * i = 0.44 m * 0.3 m * 5 m * 2500 Kg/ m2 = 1650Kg
gP = H * b * 2500 Kg/m2 * i = 3 m *( 0.3 m) 2 * 2500 Kg/ m2 = 675 Kg
N1 = 16196.6 Kg + gT1 = 16196.6 Kg + 1500 Kg = 17696.6 Kg 176966 N
N2 = N1+ 21478.1 Kg + gT2 + gP = 17696.6 Kg + 21478.1 Kg + 1650 Kg + 675 Kg =
= 41499.7 Kg 414997 N
N3 = N2+ 21478.1 Kg + gT3 + gP = 41499.7 Kg + 21478.1 Kg + 1650 Kg + 675 Kg =
= 65302.8 Kg 653028 N
PROGETTO DEL PILASTRO del PRIMO PIANO MAGGIORMENTE SOLLECITATO
N = 653028 N Pilastro a sezione quadrata
Prendo:
- ACCIAIO Fe b 44 k
- CLS Rbk 35 N/mm2
ss =260 N/mm2
Rbk -15
sc = 0.7 (6 + ) = 7.7 N/mm2
4
Acsn = N / sc = 653028 N / 7.7 N/mm2 = 84808.83 mm2
bmin = Acsn = 84808.83 mm2 = 291.21 mm
SCELGO LA BASE : b = 300 mm
Ac = b 2 = 3002 mm 2 = 90000 mm2
SCELGO As (comunque >
As > 0.8 / 100 * 84808.83 mm2 678.47 mm2
0.3 / 100 * Ac As 5400 mm2
SCELGO 4 16 con As = 804 mm2
VERIFICA DI RESISTENZA:
Ao = A c + n *As = 90000 mm2 + 15 * 804 mm2 = 102060 mm2
sc = N/ Ao = 653028 N / 102060 mm2 = 6.2 N/mm2 VERIFICATO
sS = n * N/ Ao = 15 * 653028 N / 102060 mm2 = 95.85 N/mm2
95.85 N/mm2 < 260 N/mm2 VERIFICATO
VERIFICA DELLA SNELLEZZA:
Imin b / 12 = (300 mm) 4 / 12 = 675000000 mm4
rmin Imin Ao = 675000000 mm4 / 102060 mm2 = 81.32 mm
l Max = l0 / rmin = 3000 mm / 81.32 mm = 36.89
< l Max <
NON E' UN ELEMENTO SNELLO, QUINDI BASTA FARE LA VERIFICA di RESISTENZA.
gT1 = H * b * 2500 Kg/m2 * i = 0.4 m * 0.3 m * 2.25 m * 2500 Kg/ m2 = 675 Kg
gT1' = H * b * 2500 Kg/m2 * i = 0.68 m * 0.55 m * 6 m * 2500 Kg/ m2 = 5610 Kg
gT2 = H * b * 2500 Kg/m2 * i = 0.44m * 0.3 m * 2.25 m * 2500 Kg/ m2 = 742.5 Kg
gT2' = H * b * 2500 Kg/m2 * i = 0.62m * 0.7 m * 6 m * 2500 Kg/ m2 = 6510
gT3 = H * b * 2500 Kg/m2 * i = 0.44 m * 0.3 m * 2.25m * 2500 Kg/ m2 = 742.5 Kg
gT3' = H * b * 2500 Kg/m2 * i = 0.62 m * 0.7 m * 6m * 2500 Kg/ m2 = 6510 Kg
gP = H * b * 2500 Kg/m2 * i = 3 m *( 0.4 m) 2 * 2500 Kg/ m2 = 1200 Kg
N1 = 3953.4 Kg + 15456 Kg + gT1 + gT1 ' =
= 3953.4 Kg + 15456 Kg + 675Kg + 5610 Kg = 25694.4 Kg 256944 N
N2 = N1+ 5242.6 Kg + 20496 Kg + gT2 + gT2 '+ gP =
= 25694.4 Kg + 5242.6 Kg + 20496 Kg + 742.5 Kg + 6510 Kg + 1200 Kg=
= 59885.5 Kg 598855 N
N3 = N2+ 5242.6 Kg + 20496 Kg + gT3 + gT3 '+ gP =
= 59885.5 Kg + 5242.6 Kg + 20496 Kg + 742.5Kg + 6510 Kg + 1200 Kg =
= 94076.6 Kg 940766 N
PROGETTO DEL PILASTRO del PRIMO PIANO MAGGIORMENTE SOLLECITATO
N = 940766 N Pilastro a sezione quadrata
Prendo:
- ACCIAIO Fe b 44 k
- CLS Rbk 35 N/mm2
ss =260 N/mm2
Rbk -15
sc = 0.7 (6 + ) = 7.7 N/mm2
4
Acsn = N / sc = 940766 N / 7.7 N/mm2 = 122177.4 mm2
bmin = Acsn = 122177.4 mm2 = 349.53 mm
SCELGO LA BASE : b = 400 mm
Ac = b 2 = 4002 mm 2 = 160000 mm2
SCELGO As (comunque >
As > 0.8 / 100 * 122177.4 mm2 977.42 mm2
0.3 / 100 * Ac As 6 / 100 mm2
480 mm 2 As 9600 mm2
SCELGO 4 con As = 1257 mm2
VERIFICA DI RESISTENZA:
Ao = A c + n *As = 160000 mm2 + 15 * 1257 mm2 = 178855 mm2
sc = N/ Ao = 940766 N / 160228 mm2 = 5.25 N/mm2
5.25 N/mm2 < 7.7 N/mm2 VERIFICATO
sS = n * N/ Ao = 15 * 940766 N / 178855 mm2 = 78.9 N/mm2
78.9 N/mm2 < 260 N/mm2 VERIFICATO
VERIFICA DELLA SNELLEZZA:
Imin b / 12 = (400 mm) 4 / 12 = 2133333333 mm4
rmin Imin Ao = 2133333333 mm4 / 178855 mm2 = 109.21 mm
l Max = l0 / rmin = 3000 mm / 109.21 mm = 27.47
< l Max <
NON E' UN ELEMENTO SNELLO, QUINDI BASTA FARE LA VERIFICA di RESISTENZA.
FONDAZIONI
- IN CORRISPONDENZA DEL PILASTRO DI 30 cm
gP = H * b * 2500 Kg/m2 * i = 3 m *( 0.4 m) 2 * 2500 Kg/ m2 = 1200 Kg
N = 653028 N + gP = 65302.2 Kg + 675 Kg = 65977.8 Kg
PORTANZA TERRENO sT = 1 Kg/cm2
bmin N/ sT 65977.8 Kg 1 Kg/ cm2 = 256.86 cm
SCELGO UNA BASE b = 300 cm
H a = (b - b*p) / 2 = ( 300 cm - 30 cm ) / 2 = 135 cm
VERIFICA
PESO FONDAZIONE : Pf = g * H * b2
= 2400 Kg/ m2 * 1.35 m * (3 m) 2 = 29160 Kg
N + Pf 65977.8 Kg + 29160 Kg
= 1.05 Kg/ cm2
b2 (320 cm ) 2
1.05 Kg/ cm2 > 1 Kg/ cm2 (sT NON VERIFICATO
SCELGO UNA BASE b = 320 cm
H a = (b - b*p) / 2 = ( 320 cm - 30 cm ) / 2 = 145 cm
VERIFICA
PESO FONDAZIONE : Pf = g * H * b2
= 2400 Kg/ m2 * 1.45 m * (3.2 m) 2 = 35635.2 Kg
N + Pf 65977.8 Kg + 35635.2 Kg
= 0.992 Kg/ cm2
b2 (320 cm ) 2
0.992 Kg/ cm2 < 1 Kg/ cm2 (sT VERIFICATO
FONDAZIONI
- IN CORRISPONDENZA DEL PILASTRO DI 40 cm
gP = H * b * 2500 Kg/m2 * i = 3 m *( 0.4 m) 2 * 2500 Kg/ m2 = 1200 Kg
N = 940766 N + gP = 94076.6 Kg + 1200 Kg = 95276.6 Kg
PORTANZA TERRENO sT = 1 Kg/cm2
bmin N/ sT 95276.6 Kg 1 Kg/ cm2 = 308.66 cm
SCELGO UNA BASE b = 450 cm
H a = (b - b*p) / 2 = ( 450 cm - 40 cm ) / 2 = 205 cm
VERIFICA
PESO FONDAZIONE : Pf = g * H * b2
= 2400 Kg/ m2 * 2.05 m * (4.5 m) 2 = 99630 Kg
N + Pf 94076.6 Kg + 99630 Kg
= 0.95 Kg/ cm2
b2 (450 cm ) 2
0.95 Kg/ cm2 < 1 Kg/ cm2 (sT VERIFICATO
DIMENSIONAMENTO FONDAZIONI
- IN CORRISPONDENZA DEL PILASTRO HE 180 A , RIFERITO ALLA DOPPIA
CAMPATA 450-550 cm.
gP = 3 m * 35.5 Kg/ m2 = 106.5 Kg
PORTANZA TERRENO sT = 1 Kg/cm2
bmin N/ sT 69568.1 Kg 1 Kg/ cm2 = 263.7 cm
SCELGO UNA BASE b = 270 cm
H a = (b - b*p) / 2 = ( 270 cm - 18 cm ) / 2 = 126 cm
VERIFICA
PESO FONDAZIONE : Pf = g * H * b2
= 2400 Kg/ m2 * 1.26m * (2.7 m) 2 = 22044.96 Kg
N + Pf 69568.1 Kg + 22044.96 Kg
= 1.25 Kg/ cm2
b2 (270 cm ) 2
1.25 Kg/ cm2 > 1 Kg/ cm2 (sT NON VERIFICATO
SCELGO UNA BASE b = 350 cm
H a = (b - b*p) / 2 = (350 cm - 18 cm ) / 2 =166 cm
VERIFICA
PESO FONDAZIONE : Pf = g * H * b2
= 2400 Kg/ m2 *1.66 m * (3.5 m) 2 = 48804 Kg
N + Pf 69568.1 Kg + 48804 Kg
= 0.96 Kg/ cm2
b2 (350 cm ) 2
0.96 Kg/ cm2 < 1 Kg/ cm2 (sT VERIFICATO
Privacy |
Articolo informazione
Commentare questo articolo:Non sei registratoDevi essere registrato per commentare ISCRIVITI |
Copiare il codice nella pagina web del tuo sito. |
Copyright InfTub.com 2025